Railway Loadout Designs for Grain Facility2018-07-03T15:10:54+00:00

Project Description

Railway Loadout Designs for Grain Facility

ADM Truck and Rail Loadout Upgrades
  • LOCATION: Gilman, IL

  • CLIENT: Midwest Grain Facility

Railway engineering services and loadout designs were performed by TWM for this project for a Midwest grain company. Our topographic survey verified existing conditions so we could propose dimensions for construction of a new  60,000 bushel per hour bulk weigher and loadout system. TWM verified the location of existing column lines, centerline of the railroad, existing workhouse structure, discharge flange of south upper garner, and various floor elevations within the work-house structure.  Based on  field measurements TWM marked cutout areas on the existing floors and walls within the structure for proposed spouting locations and marked beam connection points on the wall of the workhouse structure at proposed elevations.

Go to Industry.

Exceptional Service. Nothing Less.