1981-2021 Snapshot:

Wastewater treatment is often out of sight and out of mind—until a growing community needs more capacity, aging infrastructure needs attention, or new environmental demands require a different approach.

Planning for What Flows Next
For the Village of Swansea, those concerns meant taking a closer look at their entire wastewater collection and treatment system. As the community expanded and the demands on its wastewater system continued to change, the Village needed a plan to increase capacity, address long-term needs, and make smart use of the infrastructure already in place. And for TWM, it meant building on a relationship and a facility that had already been shaped by decades of forward-thinking infrastructure improvements.

The result was designed to do more than simply add capacity. It was about determining the right path forward for the entire system.

Forward From the Start
TWM had been part of the facility’s evolution for decades, designing previous expansions and improvements in 1983 and 1995. That history included a notable step forward in wastewater treatment technology, with TWM designing an Ultra-Violet (UV) light disinfection system that was among the first municipal systems of its kind implemented in Illinois.

Years later, in 2004, that same spirit of innovation would once again help shape the plant’s future. For this expansion phase, the team performed flow monitoring and an inflow and infiltration study across 10 sub-basins, assessed existing lift stations, developed growth and flow projections, and evaluated the long-term needs of both the collection and treatment systems.

Just as importantly, the team evaluated multiple treatment alternatives—including membrane bioreactors, extended aeration, and sequencing batch reactors—considering not only initial construction costs but also the long-term maintenance requirements that would shape the facility for years to come.

Rethinking What Was Already There
One of the most important parts of the expansion wasn’t something entirely new. Instead, TWM found new purpose in the infrastructure that was already there. The selected approach increased the plant’s design capacity from 2.7 million gallons per day to 5.0 million gallons per day—an 85% increase.

The facility’s existing extended aeration tanks were converted into Sequencing Batch Reactors, or SBRs, with provisions for biological nutrient removal. By reusing and repurposing the existing tanks, the project helped maximize the value of infrastructure already in place while providing the treatment capabilities needed to support the facility’s future.

Around those improvements, the project added the infrastructure needed to support the plant: a sludge handling facility, headworks and terminal lift station, and new office and laboratory. Even the plant’s pioneering UV disinfection system was brought forward, upgraded to continue serving the expanded facility.

A Foundation for the Future
With support from State Revolving Fund financing, the expansion transformed years of planning into a facility prepared to meet Swansea’s future needs. From collection system studies and long-term planning to treatment technology evaluations and facility design, the project brought together every part of the wastewater system to create a coordinated path forward.

With an 85% increase in treatment capacity, the project represented a continued evolution—rooted in thoughtful planning, innovation, and a willingness to see new potential in existing infrastructure.

The project also represented something larger for TWM: the opportunity to help a client build on past investments while preparing for a new chapter. Decades after helping shape the facility’s earlier improvements, TWM strategically reimagined its capacity, technology, and capabilities for the years ahead. The result was more than an expanded treatment plant, it gave the City of Swansea a stronger wastewater system and the foundation to handle whatever challenges come next.